Good day Team,
Got an easy one for you, I got Exchange 2010 (2 Edge in DMZ, 2 CAS, 2 Hub (all virtual) and 2 Mailbox - physical connected to DAS boxes), got a DAG configured in between.
Question - got a task to move these servers to another building (shifting), what procedure is recommended to plan for the move of Exchange 2010 servers in DAG, do i need to stop the replication between the server and move them one by one to another site, bring that site up with the one set and then move the other set?
To stop the replication between the Mailbox server, what is the recommended commands, procedure one should be look for?
Thanks
-Inderjit