Hello,
In MS Project i'd like to add resources to tasks, but this results in some problems
For example i have 1 person (Daan) scheduled on a task for 5%.
But i the resourcesheet MS project has scheduled him 40 hours a week for the first task.
Why does MS project schedule him for 40 hours in stead of the 2 hours a week (5%) i filled in?
With kind regards,
Erwin