Change unit work hours for just one day, while in the middle of a task
Hello,
Suppose i have a task (let's call it X) from monday to friday, which is 40 hours work. I assign a resource named "John Smith" to the task.
A different need occurs and John is assigned another task (let's call it Y) which will take place on Wednesday for half the day (4 hours).
Therefore, X needs to be extended until next Monday for 4 hours (until noon probably) and Y will require John's 4 hours in Wednesday.
Regarding X task, is there a way to change John's work hours for Wednesday only and leave the rest untouched?
I can't seem to find an option to change John's work hours for just one day.
Thank you in advance.