Change unit work hours for just one day, while in the middle of a task
Hello, Suppose i have a task (let's call it X) from monday to friday, which is 40 hours work. I assign a resource named "John Smith" to the task. A different need occurs and John is assigned another task (let's call it Y) which will take place on Wednesday for half the day (4 hours). Therefore, X needs to be extended until next Monday for 4 hours (until noon probably) and Y will require John's 4 hours in Wednesday. Regarding X task, is there a way to change John's work hours for Wednesday only and leave the rest untouched? I can't seem to find an option to change John's work hours for just one day. Thank you in advance.
May 20th, 2012 10:02am